This process is based on a two story residential home.

  • icon

    CHOOSE A STAND

     1 week

    Who came first – chicken or the egg? builder or the architect? We say the informed customer came first! Buying a stand is all about $, size, layout (NorthEastSouthWest facing?), servitudes, estates rules & architectural guidelines – your builder & architect needs to know their stuff.

  • icon

    WHICH ARCHITECT?

    2 weeks or more

    How much will he charge for MY idea? single or double storey? Plastered walls or Facebrick, Wood or Aluminium doors & windows? How do I minimise Yearly & Monthly Maintenance? Green Footprint -solar geyser? gas geyser? heatpump? gas stove? Grey water system? Insulation? Cavity walls? Double glazing windows? Underfloor heating or Gas Fireplace? How many bedrooms & ladies how much cupboard space is enough?, bathroom layout & sanitary ware that saves water? Living & Entertainment? Bar? Study? Garage & Storage? Servants quarters? Future possibilities for extension like a extra room or swimming pool? Where is what light installed and what light switches goes where? How high is my shower head and how wide is my bath – will it fit practically like the architect indicated? Cornice mould? Skirting size? Type of Floor & Wall tile? Bedrooms – carpets or laminates? Kitchen planning & layout? wall color choices? #&%$ this is too much!!

But wait we can help…we help with the design & its included in our price! That’s not all we also assist with…

  • icon

    INTERIOR PLANNING

    1 day

    We supply a mood board to help visualize the final product vs. budget.

    Get a FREE Interior Design Consultation at Floornament at Shop nr 5 in Eco Boulevard (www.floornament.com)

  • icon

    BUILDER QUOTATION

    1 week

    All the above questions affects Rand per m2 – Builders tender & documents (contract)

  • icon

    BANK DOCUMENTS

    1 week

    All banks need different documentation but most want a Bank Agreement, Tender & Contract with a Builder, Waiver of Lien, NHBRC Enrollment & Registration, Interest letter, etc.

  • icon

    APPROVAL FROM BANK

    1 week

  • icon

    ATTORNEY INSTRUCTION

    1 day

    Client signs all documentation with the attorney.

  • icon

    HOME OWNERS ASSOCIATION APPROVAL

     Up to 2 weeks

  • icon

    COUNCIL APPROVAL

  • icon

    NHBRC SUBMISSION

    Up to 2 weeks

    Depending on the soil conditions, area & NHBRC engineers.

    Tshwane 4-6 Weeks
    Ekurhuleni 6-8 Weeks
    Jo’burg up to 12 Weeks

  • icon

    ATTORNEY REGISTERS STAND AND BUILDING BOND

    6 to 8 weeks

Once all the above ducks are in a row we GO GO GO…

OK, now we start:

  • icon

    PROJECT PLANNING

    1 week

    WHEN must we order WHAT to fit the budget

  • icon

    HOME OWNERS ASSOCIATION

    1 week

    Approves site establishment

  • icon

    SITE ESTABLISHMENT

    1 week

    We clear the site of all rubble & grass, Land surveyor for stand beacons and house points, Temporary power & Toilet facilities, Water Connection & storage facilities

  • icon

    CONSTRUCTION STARTS

    2 days

    Excavate trenches, sewer & boundary wall

    1 day

    Engineer Council HOA & Bank inspect trenches

    3 days

    Engineer designs foundation – steel ordered

    1 week

    Compaction of trenches & fixing of steel

    1 day

    Concrete in foundations

Progress payment $$$$ – the first one can take up to 3 weeks

  • icon

    BUILDING FOUNDATION WALLS

    1 week

    Backfill & level inside of foundation walls to prepare for surface bed steel & concrete Once leveled plastic is installed for waterproofing & welded mesh for surface bed strength.

    Installation of electical conduit for plugs & light switches & plumbing wastes for bath shower & basins.

    2 weeks

    Pouring of concrete for the surface bed.

    1 day

  • icon

    BUILDING GROUND FLOOR WALLS

    2 weeks

    Building of ground floor external and internal walls, including lintels and brick force. To prepare for 1st floor slab.

  • icon

    SLAB PREPARATION

    2 weeks

    Preparing for the 1st floor slab.

Progress payment $$$$ – this can take 2 weeks
  • icon

    BUILDING FIRST FLOOR WALLS

    2 weeks

    Building of first floor external and internal walls, including lintels and brick force. To prepare for roof installation.

  • icon

    ROOF

    Installation

    1 week

    Erect Trusses & Insulation

    1 – 2 days

    Install roof tiles

    1 – 2 days
Progress payment $$$$ – this can take 2 weeks
  • icon

    BUILDERS TO FINISH

    2 weeks

    Building Internal Door Frames, Beam filling, Gables, Window Sills, Braai, Fireplace, Boundary & Screen Walls.

  • icon

    CLIENT INSPECTS

    Planned Plumbing & Electrical points before plaster.

    1 day

    Plumber & Electrician installs Geyser & Main Power supply, conduit, pvc pipes & copper into Ground floor & First Floor walls.

    2 weeks
  • icon

    INSTALLING

    1 week
    Wooden or Aluminium Windows + Garage Door – Prepare for installation of outside doors to lock the house.
  • icon

    PLASTER

    4 weeks
    Team starts inside with the walls & Floor screed
  • icon

    CEILINGS

    3 weeks

    Ceilings are now installed – Rhinolite on the ceiling starts in the first finished room.

Progress payment $$$$ – this can take 2 weeks
  • icon

    PAINTERS ARRIVE

    6 weeks

    Painter starts with waterproofing & the BEST primer money can buy (off course this is included).

    Client chooses final sample colour for inside, outside and a matching tile.

  • icon

    TILERS ARRIVE

    6 weeks
    First Floor Tiles and then Bathrooms.
  • icon

    INTERNAL DOORS

    2 weeks
    Internal Doors & Wooden skirting are installed.
  • icon

    PLASTER TEAM

    3 weeks
    Starts and finishes outside.
Progress payment $$$$ – this can take 2 weeks
  • icon

    KITCHEN

    8 weeks

    Cupboards, built in cupboards & granite installed.

  • icon

    CEILING GUY

    2 weeks

    Finishing cornices.
  • icon

    PAINTER

    1 week

    Painter touches up inside & out.

  • icon

    ELECTRICAL

    2 weeks

    Final Electrical, Stove & Light fittings installed.

  • icon

    BATHROOM

    2 weeks
    Final bathroom fittings installed.
  • icon

    PAINTER

    1 week

    Painter touches up inside & out.

  • icon

    ELECTRICAL

    2 weeks

    Final Electrical, Stove & Light fittings installed.

  • icon

    BATHROOM

    2 weeks
    Final bathroom fittings installed.
Progress payment $$$$ – this can take 2 weeks
  • icon

    STAIRCASE BALUSTRADES & GARDEN GATES

    1 day

  • icon

    SHOWERS, MIRRORS AND BATHROOM ACCESSORIES

    2 days

  • icon

    PREPARE FOR IRRIGATION BEFORE PAVING

    1 week

  • icon

    CLEARING

    3 weeks
    Level & Clear site of Final Rubble, Install New Topsoil, Grass & Trees.
  • icon

    FLOORING

    1 day
    Laminate or Carpet Flooring in the Bedrooms are installed last.
  • icon

    INSPECTIONS

    1 day

    Final Inspections for Occupation Certificate -Inspections – Council needs Certificate of completion for Foundation, First Floor Slab, Roof, Glazing, Gas, Electricity & Plumbing.

  • icon

    CLEANERS

    3 days

    Starts scrubbing & the client starts packing & get ready to move.